Terms and Conditions
1. Contractor shall not be liable for delays caused by weather conditions, strikes, delays in obtaining goods, or any other causes beyond its control.
2. The details specified in this contract contain the entire understanding and agreement between the parties. No verbal agreements or changes will be recognized.
3. Contractor will execute this contract by promptly processing and expediting work schedules so that the necessary arrangements are made for timely completion of the work to be performed under the terms of this contract at earliest possible date. In consideration of this, Owner agrees that this contract is binding and non-cancelable 72 hours following the date of execution. If, for any reason, the Owner shall attempt to cancel this contract, Owner agrees to pay Contractor one-third (1/3) of the full contract price as liquidated damages to Contractor for said unauthorized cancellation.
4. In the event Owner fails to make payments as required herein, then from the date due until paid in full, the delinquent payment shall bear interest of two percent (2%) per month or part thereof. In addition, should it become necessary for Contractor to consult an attorney or take legal action to collect payments, Owner shall pay all reasonable attorneys’ fees and other costs incurred by Contractor herewith.